What is the amount of time that a task can be delayed without affecting subsequent tasks?

As per PMBOK the Float is defined as: The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.

It can be calculated in two ways:

Float = Late Start - Early Start

OR

Late Finish - Early Finish

Critical Activities (activities on the Critical Path) usually have a Float of Zero

by Ahmed Khater , ID& Fit- Out Construction Manager , Harmony Atelier Interior Design& Decoration
6 years ago

Float or slack is the amount of time between early start and late start for an activity

e.g. if you can now start an activity (which take one week to complete ) and its OK to complete it within3 weeks without delaying the completion of the project so the float here =2 weeks   

buffer time to complete the task or activity without causing delay to its interdependent tasks. Thanks.

by Ajaya Mohanty Ajaya , District Project Officer , Odisha State Disaster Management Authority
6 years ago

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float") project completion date ("total float").

What is the amount of time that a task can be delayed without affecting subsequent tasks?

by Fawzan Malas , Senior IT Consultant , Jumia Algeria
6 years ago

Float or slack time is the amount of work periods an activity can be delayed without causing an overall delay to the project.

There are two types of float: total float and free float. Total float is the amount of time you can delay the earliest start of a task without delaying the ending of the project. 

Free float is the amount of time you can delay the start of a task without delaying the earliest start of a successor task.

What is the amount of time that a task can be delayed without affecting subsequent tasks?

by ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company
6 years ago

This is the time duration to which the activity can be delayed without affecting the project duration

by Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality
6 years ago

I think that the subject needs some details ;-

Free slack or free float is different than Total Float Free Float is the time an activity can be delayed without delaying its subsequent activities Total Float is the time an activity can be delayed without delaying the project completion date.

There is no float time for activities on the critical path, that's why they are identified as being critical.

by د Waleed , Management - Leadership-Business Administration-HR&Training-Customer Service/Retention -Call Center , Multi Companies Categories: Auditing -Trade -Customer service -HR-IT&Internet -Training&Consultation
6 years ago

I would agree with provided answers... Helpful information ... Thank You !

Float, is the time between the planned completion date of an activity in the schedule, and the date where it will become a critical path activity.  Essentially, the extra time allowed in the schedule for an activity, before it will start to affect the overall completion date.

by Ansu Batabyal , DESIGN ENGINEER , TATA CONSULTING ENGINEERS LTD.
6 years ago

Schedule the project in bottom up approach with realistic time. Make more parallel activity with additional man power. Crash the schedule.  

Popular Searches

Learning Objective

  1. Calculate critical path, project float, early start dates, and late start dates.

The critical path is the path through the network that results in the latest completion date of the project.

If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount. It is the path with the greatest total duration. To determine the critical path, add the amount of time estimated for the duration of each activity to the previous activity to determine which path through the network has the longest total duration, as shown in Figure 8.15 “Critical Path”. Durations are indicated in days. The critical path through these tasks takes at least eight days. Activities on the critical path are shaded.

Figure 8.15 Critical Path

What is the amount of time that a task can be delayed without affecting subsequent tasks?

Early Start Dates

Starting dates can be assigned to each activity by doing a forward pass proceeding from left to right in the network diagram beginning with the project start date. The dates derived by this method are the early start (ES) dates. The early start date for an activity is the earliest date the activity can begin. The estimate considers durations and resource availability calendars. To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have no predecessor activities. Follow these steps to calculate the early start dates of subsequent activities, assuming finish-start relationships:

  • Add the predecessor activity’s duration to its start date.
  • Add the lag time or subtract the lead time.
  • Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and add the number of off-days that the activity would span on those calendars.
  • Assign the calculated date as the early start date of the successor activity.

Forward Pass for John’s Move

John begins planning his move to Atlanta the same day he accepts the job. The start date in this example is Monday, November 29, 2010. Tasks 1.1 and 2.1 can both start on that day, so the early start dates for tasks 1.1 and 2.1 are November 29. John calculates the early start date for the activities. A partial list is provided below. Compare the figure below and the figure in the next sidebar. Observe that John is willing to work on weekends, but activity 2.2.3 is delayed by two days because one of the moving companies did not provide bids on the weekend. Observe that activity 2.3 has a lead time of one day, but that relationship is between activity 2.1 and 2.3. The network path from activity 1.3 is longer, so the lead time with activity 2.1 is not considered in calculating the early start date of 2.3.

Figure 8.16 Early Start Dates Determined by a Forward Pass

CodeDescriptionPredecessorsRelationshipsLead/LagResourcesDurationEarly Start Date
1aContact Dion and Carlita None 0 J,D,C
.25 hr each
2 d 11/29
1bHost planning lunch 1a FS
(Finish/Start)
0 J,D,C
2 hr each
1 d 12/1
1cDevelop and distribute schedule 1b FS 0 J 2 hr 1 d 12/2
1dMake hotel arrangement in Atlanta 1a FS 0 J .5 hr 1 d 11/30
2aGather packing material None 0 D 2 hr 1 d 11/29
2biContact van companies and get 3 bids 1c FS 2 d 12/3
2bii2bi FS 0 J .5 hr 1 d 12/7
2biiiSign moving contract 2bii FS 1 d 12/8
2cPack small and delicate items 1c
2a
FS
FS
-1 C 6 hr 1 d 12/3

Doing this process manually is error prone and time consuming. Fortunately, there are computer programs to assist in the process, but the project manager must understand the process well enough to recognize computer errors. Computer software must be combined with common sense or good judgment.

Float

Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

Total Float

Total float is the difference between the finish date of the last activity on the critical path and the project completion date. Any delay in an activity on the critical path would reduce the amount of total float available on the project. A project can also have negative float, which means the calculated completion date of the last activity is later than the targeted completion date established at the beginning of the project.

Float in John’s Move

The last activity in John’s move has an early start date of December 28 and a duration of one day. John could start work on Wednesday, December 29. John’s first day at work is Monday, January 3, so the project has a total float of five days.

Figure 8.17 Total Project Float

What is the amount of time that a task can be delayed without affecting subsequent tasks?

Late Start Dates

The next step is to work through the network diagram from right to left beginning with the mandated completion date, which is a milestone that is set in the project plan. Subtract the duration of each activity in each path to determine the latest date the activity could begin and still meet the project completion date. Resource calendars must be considered in the backward pass as well as the forward pass.

To calculate late start dates, begin with the project completion milestone and assign that date as the finish date of its predecessor activities. Follow these steps to calculate the late start dates of predecessor activities, assuming finish-start relationships:

  • Subtract the predecessor activity’s duration from its late finish date.
  • Subtract the lag time or add the lead time to the late finish date.
  • Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and subtract the number of off days that the activity would span on those calendars.
  • Assign the calculated date as the late start date of the predecessor activity.

The difference between the early start date and the late start date for activities on the critical path is usually the same as the total float, unless the activities are affected by the resource calendars differently in the forward and backward pass. For example, if a piece of key equipment is only available for a few days, activities that depend on it have the same start and finish dates in the forward and backward passes.

Free Float

If activities that are not on the critical path have a difference between their early start date and their late start date, those activities can be delayed without affecting the project completion date. The float on those activities is called free float.

Key Takeaway

  • To calculate total project float, begin at the start date and add the duration of each activity in each possible path through the network diagram, including nonworking days from the resource calendars, to determine the early project end date. The longest path through the network is the critical path. The difference between the early end date and the required completion date of the project is the total project float, and the start date of each activity is the early start date. To calculate the late start dates, begin with the required project completion date and work backward, subtracting the duration of each activity through each possible pathway.

Exercises

  1. The path through the network diagram that has the longest total duration is the __________ path.
  2. The difference between the sum of the activity durations along the critical path and the project completion date is the project _______.
  3. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _________ time.
  4. If the last activity in the critical path has a completion date that is five days later than the project completion date, the project has a _______ _________ (two words) of five days.
  5. What is the difference between free float and project float?
  6. If an activity has a duration of three days, how do you calculate the finish date in a way that considers availability of the resources for that activity?
  7. What would be an example of lag time between two activities?

Project Float

Consider a project in which you have been involved that experienced unexpected delays. Describe how the project’s manager dealt with the delays. Specifically, consider if the delay was due to an activity that was on the project’s critical path, if people or resources were diverted from other tasks, or if free float existed in the original schedule. Describe the ultimate effect on the project’s completion date.

What is the amount of time that a task can be delayed without affecting the subsequent task?

In project management, “float” or “slack” is the amount of time a task can be delayed without affecting the deadlines of subsequent tasks or the project's final delivery date. The former is called “free float”, and the latter is called “total float”. Besides, there are two popular tools carrying the same names.

Which is the amount of time an activity can be delayed?

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.

Is the amount of time an activity can be delayed without delaying?

Total Float (TF) It is the amount of time by which an activity can be delayed without delaying the project duration.

Is the maximum length of time that an activity can be delayed without delaying the entire project?

Slack is the amount of time an activity can be delayed without delaying the entire project.