The best method for establishing the existence of resource conflicts across project activities uses:

8) What information is usually provided on a resource-usage calendar?

A) The tasks, the precedence requirements, and the money per unit time needed to reduce them.

B) The personnel, their hourly wage or salary, and the number of hours per week they are available.

C) The personnel, their responsibility for certain tasks, and the number of hours per week they are available.

D) The tasks, the people and equipment available, and the ownership and reporting relationships among them.

What information is usually provided on a resource usage calendar?

12) What information is usually provided on a resource-usage calendar? A) The tasks, the precedence requirements, and the money per unit time needed to reduce them. B) The personnel, their hourly wage or salary, and the number of hours per week they are available.

Which of the following represents the best definition for resource leveling?

268. Which of the below represents the BEST definition for resource leveling? A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.

When several activities need the same limited resource at the same time the activities with?

Project Management Ch. 6 Flashcards.

What represents the amount of work delayed due to unavailable resources?

94) In-process inventory represents the amount of work waiting to be completed but delayed due to unavailable resources.